Overview:
The furnace body adopts a fully enclosed structure, achieving atmosphere sintering in the furnace chamber. It meets the sintering needs of various workpieces, has a wide application market, flexible usage methods and means, and broad development prospects. It is very suitable for small batch production and trial manufacturing in factories and research units.
1. Application:
High-temperature sintering processes for advanced ceramic materials such as ITO targets, ceramic filters, zirconia ceramic ferrules, ceramic smartphone casings, wearable ceramic components, and CIM (Ceramic Injection Molding).
2.Parameters and Features:
Effective furnace chamber size: 1600×1250×800mm (D×H×W)
Temperature range: RT~1400ºC, maximum temperature 1500ºC
Heating method: Heating elements
Temperature zones: 1
Insulation material: Alumina products/ceramic fiber materials
Atmosphere: Air/oxygen
Control points: 6
Control instrument: Chino KP1000 temperature controller
Operating power supply: 220/380VAC 50Hz
Maximum power: 180kW
Equipment weight: Approximately 10000kg
3. Delivery List
Table 1 Delivery list |
|
Item |
Note |
Qty. |
Basic Components |
Furnace |
|
1 SET |
Inspection Certificates |
Certificates of major outsourced components |
1 SET |
Technical Documents |
Instructions, technical documents of the major outsourced parts, etc |
1 SET |
Control Cabinet |
1000×2000×600mm(W×H×D) |
1 SET |
Key Components |
Heating Plate |
U-shaped silicon molybdenum heater |
1 SET |
Flow Meter |
TOFCO |
1 SET |
Thermocouple |
THERMOWAY |
1 SET |
Lifting System |
|
1 SET |
Temperature Control Module |
Azbil |
1 SET |
PLC |
SIEMENS |
1 SET |
Touch Screen |
MCGS |
1 SET |
Spare Parts |
Heating Element |
U-shaped silicon molybdenum heater |
1 PC |
4.Equipment Installation and Usage Conditions
- The equipment must be installed indoors, with an ambient temperature of 0ºC~40ºC. The indoor environment should be free of flammable gases, corrosive gases, and steam.
- The equipment requires a floor area of no less than 20 square meters, with a working space length of no less than 5 meters, width of no less than 4 meters, and height of no less than 4 meters. The foundation should be solid and level, with a total furnace weight of approximately 10000kg.
- The power supply for the furnace must be a three-phase five-wire AC power line, 240kVA, 220/380±10%VAC, 50±2%Hz. This power line should be dedicated, and large power conversion equipment such as welding machines, electric furnaces, and metal cutting machines should not be connected to this distribution.
- The equipment must be reliably grounded.